Download Document | |
Document Type: | General |
Publish Date: | April 2020 |
Primary Author: | Audit Scotland |
Edited By: | Arsalan Hasan |
Published By: | Audit Scotland |
Good progress has been made towards the Scottish Government’s ambitious target to deliver 50,000 new affordable homes between April 2016 and March 2021. Of these, 35,000 will be social rented homes provided by councils and Registered Social Landlords (RSLs). By December 2019, 31,136 homes had been completed including 20,336 homes for social rent. The Scottish Government plans to invest around £3.5 billion to meet the target. Over the first three years of the programme, it has spent around £1.9 billion. Councils and RSLs have also invested significant sums.